CalTrain Construction September 26th - October 2nd

Posted on September 27, 2015 at 5:55 PM

CalTrain will continue construction, installation and maintenance as part of the San Francisco Roadway Bridges Project for seven days, starting September 7th. Most construction will be between 7 AM and 5 PM.

 

There will be night work on the 23rd Street Bridge until October 1st.  At the Paul Avenue Bridge, night work is also scheduled on September 30th. Crews will be installing the utility support bridge.

 

There is no work scheduled for the Jerrold Avenue Bridge. From September 28th to October 2nd, crews will install column framework.

 

At the Paul Avenue Bridge this week, from September 28th to October 2nd, crews will transfer utilities to the temporary support structure


For more information, visit www.caltrain.com.

Categories: CalTrain, San Francisco

Post a Comment

Oops!

Oops, you forgot something.

Oops!

The words you entered did not match the given text. Please try again.

Already a member? Sign In

0 Comments