CalTrain Construction August 29th - September 4th

Posted on August 31, 2015 at 12:35 AM

CalTrain will continue construction, installation and maintenance as part of the San Francisco Roadway Bridges Project for seven days, starting August 29th. Most construction will be between 7 AM and 5 PM.


There will be no weekend or night work, apart from the 23rd Street Bridge from August 31st to September 4th.


There is no scheduled work for the Paul Avenue Bridge and the Jerrold Avenue Bridge this week.


From August 31st to September 4th, crews will prepare rebar and drill piles for the 23rd Street Bridge. Pedestrian and vehicle access will be blocked off. The bridge should be open in January 2016.


For more info, go to www.caltrain.com.