CalTrain Timetable Changes Effective April 4th

Posted on April 5, 2016 at 12:25 PM Comments comments (0)

CalTrain has slightly changed its timetable effective April 4th. In response, VTA will change its services to match CalTrain's new schedule on April 11th.


To view the new timetable, visit caltrain.com. To view VTA's service changes, visit vta.org.

CalTrain Approves New Fares and Parking Fees

Posted on December 9, 2015 at 5:05 PM Comments comments (0)

CalTrain is one of the fastest-growing rail systems in the Bay Area. Ridership is up over 70% from 2010. Rising maintenance & rail operations costs, plus no dedicated source of funding, has forced CalTrain to raise fares systemwide.


Fares for adults on CalTrain will rise 50 cents on February 28th, 2016. Parking will also raise by 50 cents on July 1st, 2016. Clipper passengers will still get a 15% discount. The monthly parking permit fee will also rise $5.


As a result of the fare change the Day Pass, 8-Ride Tickets, and Monthly Passes will all rise in fares as well. Discount fares will still be 50% off the adult tickets.


For more details on CalTrain's fare increase, visit www.caltrain.com,

CalTrain & SamTrans Service Changes Thanksgiving Day

Posted on November 21, 2015 at 1:50 PM Comments comments (0)

On Thanksgiving Day, CalTrain will operate a normal Sunday schedule of 32 trains, with shuttle service to and from Tamien Station. CalTrain service will stop at San Jose, not continuing south to Gilroy. There will be baby bullet trains in the morning and evening hours. 


SamTrans will operate a normal Sunday schedule, which excludes all school bus routes that do not operate on a normal Sunday. Sunday service is, of course, less frequent than weekday service.


The day after Thanksgiving, CalTrain will operate a Saturday schedule, with shuttles running to and from Tamien Station. There will be baby bullet trains. SamTrans will operate a normal non-school day service.


For more details, visit www.caltrain.com or www.samtrans.com.

Tilton Avenue Bridge to be Replaced, Bus Bridge in Place Nov. 7th

Posted on November 5, 2015 at 10:05 PM Comments comments (0)

Many CalTrain bridges are over 100 years old, including the Tilton Avenue Bridge in San Mateo. As part of the San Mateo Bridges Replacement Project, CalTrain will replace the Tilton Avenue Bridge over the weekend of November 7th and 8th, with work starting at 8 PM Friday, Nov. 6, and ending at 5 AM Monday, Nov. 9.


As crews work along the bridge, the entire CalTrain system will be affected. Since track at the Tilton Avenue Bridge will be closed, northbound trains will stop at Hayward Park, and southbound trains will stop at Burlingame. 


Between the two stations, SamTrans will operate a bus bridge connecting the two stops on November 7th. By November 8th, CalTrain trains will be able to single-track across the Tilton Avenue Bridge, eliminating the bus bridge.


Riders can expect delays during single-tracking across the bridge and while the bus bridge is in place. The next bridge to be replaced in San Mateo will be in December, at the Monte Diablo Bridge. 


For more details, visit www.caltrain.com.

CalTrain Construction October 3rd - October 9th

Posted on October 4, 2015 at 11:10 AM Comments comments (0)

CalTrain will continue construction, installation and maintenance as part of the San Francisco Roadway Bridges Project for seven days, starting October 3rd. Most construction will be between 7 AM and 5 PM.


There is no scheduled night or weekend work for both the 23rd Street Bridge and the Paul Avenue Bridge this week.


There is no work scheduled for the Jerrold Avenue Bridge. Crews may inspect the bridge site between October 5th and October 9th.


At the Paul Avenue Bridge this week, from September 28th to October 2nd, crews will transfer utilities to the temporary support structure.


Crews will continue to install column framework from October 5th to October 9th at the 23rd Street Bridge. Crews will also begin to pour concrete.


For more information, visit www.caltrain.com.

CalTrain Construction September 26th - October 2nd

Posted on September 27, 2015 at 5:55 PM Comments comments (0)

CalTrain will continue construction, installation and maintenance as part of the San Francisco Roadway Bridges Project for seven days, starting September 7th. Most construction will be between 7 AM and 5 PM.

 

There will be night work on the 23rd Street Bridge until October 1st.  At the Paul Avenue Bridge, night work is also scheduled on September 30th. Crews will be installing the utility support bridge.

 

There is no work scheduled for the Jerrold Avenue Bridge. From September 28th to October 2nd, crews will install column framework.

 

At the Paul Avenue Bridge this week, from September 28th to October 2nd, crews will transfer utilities to the temporary support structure


For more information, visit www.caltrain.com.

CalTrain Construction September 19th - September 25th

Posted on September 19, 2015 at 1:45 PM Comments comments (0)

CalTrain will continue construction, installation and maintenance as part of the San Francisco Roadway Bridges Project for seven days, starting September 7th. Most construction will be between 7 AM and 5 PM.


There will be night work on the 23rd Street Bridge from September 25th to the 26th. Crews will drill and pour piles and set rebar.


At the Paul Avenue Bridge, night work is also scheduled on September 25th. Crews will be installing utilities and the utility support bridge.


Crews will begin to restore the construction site at the Jerrold Avenue Bridge from September 21st to September 25th. 

From September 21st to September 25th, crews will prepare rebar and drill piles for the 23rd Street Bridge. Pedestrian and vehicle access will be blocked off. 


Crews will be installing utilities and the utility support bridge at the Paul Avenue Bridge September 21st to September 25th. 


For more information, visit www.caltrain.com.

CalTrain Construction September 7th - September 11th

Posted on September 7, 2015 at 3:25 AM Comments comments (0)

CalTrain will continue construction, installation and maintenance as part of the San Francisco Roadway Bridges Project for seven days, starting September 7th. Most construction will be between 7 AM and 5 PM.


There is no scheduled work for the Paul Avenue Bridge and the Jerrold Avenue Bridge this week.


From September 8th to September 11th, crews will prepare rebar and drill piles for the 23rd Street Bridge. Pedestrian and vehicle access will be blocked off. The bridge should be open in January 2016.


For more information, visit www.caltrain.com.

CalTrain Construction August 29th - September 4th

Posted on August 31, 2015 at 12:35 AM Comments comments (0)

CalTrain will continue construction, installation and maintenance as part of the San Francisco Roadway Bridges Project for seven days, starting August 29th. Most construction will be between 7 AM and 5 PM.


There will be no weekend or night work, apart from the 23rd Street Bridge from August 31st to September 4th.


There is no scheduled work for the Paul Avenue Bridge and the Jerrold Avenue Bridge this week.


From August 31st to September 4th, crews will prepare rebar and drill piles for the 23rd Street Bridge. Pedestrian and vehicle access will be blocked off. The bridge should be open in January 2016.


For more info, go to www.caltrain.com.

CalTrain Construction August 22nd to August 28th

Posted on August 23, 2015 at 11:50 PM Comments comments (0)

CalTrain will continue construction, installation and maintenance as part of the San Francisco Roadway Bridges Project for seven days, starting August 22nd Most construction will be between 7 AM and 5 PM.


There will be no weekend or night work, apart from the 23rd Street Bridge from 8 PM, August 26th, to 5 AM, August 30th.


From August 24th to August 28th, crews will prepare rebar and drill piles. Pedestrian and vehicle access will be blocked off. The bridge should be open in January 2016.


During the same dates as above, crews will install temporary abutments to the Paul Avenue Bridge. Vehicle, bicycle and pedestrian access to Paul Avenue between Gould and Carr will be blocked off.


From the 24th to the 28th, crews will install tiebacks at the Jerrold Avenue Bridge. 